Sheet 03 / FentonRoof replacement permit
It depends
Roof replacement permit
in Fenton, MO
It dependsFollow the St. Louis County re-roof rule (permit if slope under 4:12 or the covering system changes). Fenton’s published permit list has no roof permit, and we found no Fenton zoning step for it.
- Jurisdiction
- Fenton, Missouri
- Project
- Roof replacement (re-roofing)
- Issued by
- City of Fenton + St. Louis County
- Fee data
- Fees partly verified
- Checked
- Nov 28, 2026
- Sheet no.
- GP-MO-FEN-03
01
City of FentonDo you need a permit?
- Fenton’s Permit Applications page lists no roof permit, and its FAQ lists additions, remodels, fences, decks, accessory buildings and retaining walls only.[1,2]
02
What it costs
| Item | Amount | Notes & source |
|---|---|---|
| St. Louis County (building / trade permit) | ||
| Building permit fee | Table 1100.060 fee for your estimated construction cost, plus the $47 permit processing fee | Fee tables include plan review and inspection. Minimum total fee: $94 (one inspection, no plan review), $124 (with plan review), $141 (two inspections, no plan review), $171 (two inspections, with plan review).[4] |
| Extra inspections | $47 each | Plus $24 per extra half hour after the first hour of inspection time (including travel).[4] |
Fenton fees are from City checklists (zoning approval; fence dated Feb 2023). County fees: Ordinance 29,445, adopted Nov 4, 2025.
03
Where and how to apply
Community Development Department, City of Fenton
625 New Smizer Mill Road, Fenton, MO 63026
Phone 636-349-8110 · Mon–Fri 8:00 a.m.–4:30 p.m.[5]
Fenton permit applications and forms[1]
- City of Fenton: complete the St. Louis County/Municipal Zoning Approval form and pay the zoning fee (residential $25.00).
- St. Louis County: apply for the building or trade permit through the County Services Portal (aca-prod.accela.com/SLC) or call 314-615-5184.
04
What we could not verify
What we could not verify or what to confirm
- No official Fenton statement on re-roofing was found; the County rule is applied through the contract.
- County fee lines apply only when a permit is required.
- We did not find a Fenton page that says trade permits (plumbing, mechanical, electrical) also go through St. Louis County; Fenton states the County issues “building permits and related inspections”. Confirm with Community Development at 636-349-8110.
Same project, other places
05
Sources
Every figure above comes from the government pages below. Verbatim excerpts and raw downloads are archived with the site data. Not legal advice; see the disclaimer.
- Permit Applications (list of City permit forms) City of FentonChecked Nov 28, 2026 · Read through a web-fetch/search tool (the site blocks direct downloads); verbatim excerpt saved in raw/
- FAQs — Do I need a Building Permit? City of FentonChecked Nov 28, 2026 · Read through a web-fetch/search tool (the site blocks direct downloads); verbatim excerpt saved in raw/
- SLCRO Chapter 1115 Building Code §105.1, §105.1.2, §105.2 (2015 ICC codes, user-friendly edition, Ord. 27,654) St. Louis County Dept. of Transportation and Public Works · User-friendly edition dated Apr 1, 2020Checked Nov 28, 2026 · Read through a web-fetch/search tool (the site blocks direct downloads); verbatim excerpt saved in raw/Same sections appear on Municode (codified through Ord. 29,532, Feb 17, 2026): library.municode.com/mo/st._louis_county. Confirm the current adopted edition before launch.
- St. Louis County Ordinance No. 29,445 (2025), amending Chapter 1100 “Code Enforcement Fee Schedule” St. Louis County Council · Adopted Nov 4, 2025; approved Nov 5, 2025Checked Nov 28, 2026 · Full text retrieved; saved in raw/slc/Processing fees may be revised each July 31 (§1100.035).
- Community Development — About Us (Municipal Zoning Approval; County contract) City of FentonChecked Nov 28, 2026 · Read through a web-fetch/search tool (the site blocks direct downloads); verbatim excerpt saved in raw/