It depends

Often no, if the fence is 7 feet or less and in a rear or side yard. A front-yard fence, a taller fence, a pool enclosure, or an electrified or barbed-wire fence needs a permit.

Jurisdiction
St. Louis County, Missouri
Project
Fence (new or replacement fence)
Issued by
St. Louis County Dept. of Transportation & Public Works
Fee data
Fees verified
Checked
Nov 28, 2026
Sheet no.
GP-MO-SLC-02
01

Do you need a permit?

  • Permit not required for new or replacement fencing not more than 7 feet high, in the rear or side yards, except when enclosing a swimming pool, spa or hot tub.[1]
  • Fences of any height that use electrified components, barbed wire or razor ribbon are not exempt.[1]
  • Conflict between County documents: the Ordinance Guidebook says fences 6 feet or less may be installed without a building permit. Plan to the lower 6-foot figure unless the office confirms 7 feet.[2]
02

What it costs

ItemAmountNotes & source
If a permit is requiredTable 1100.060 fee for your estimated construction cost, plus the $47 permit processing feeSame building fee schedule as other residential work.[3]
$
$0

Estimate only. Computed in your browser from Table 1100.060 + the $47 processing fee, with the $94 minimum. The Code Official sets the official cost estimate and the number of inspections.

Fee schedule: Ordinance 29,445, adopted Nov 4, 2025. Processing fees may be revised each July 31.

03

Where and how to apply

Residential Building, St. Louis County Dept. of Transportation and Public Works

41 South Central Ave., 6th Floor, Clayton, MO 63105
Phone 314-615-5184 · Mon–Fri 7:30 a.m.–4:00 p.m.[4]

Apply →

St. Louis County Services Portal (Accela)[5]

  1. Start a new application in the County portal, or call Residential Building.
  2. Estimated construction cost drives the building fee; the Code Official may estimate it by square-foot cost or accept a signed contract or owner affidavit (§1100.040).
04

What we could not verify

What we could not verify or what to confirm
  • Zoning height and setback limits for fences (SLCRO Chapter 1003) were not reviewed.
  • No fee applies when the fence qualifies for the exemption.
05

Sources

Every figure above comes from the government pages below. Verbatim excerpts and raw downloads are archived with the site data. Not legal advice; see the disclaimer.

  1. SLCRO Chapter 1115 Building Code §105.1, §105.1.2, §105.2 (2015 ICC codes, user-friendly edition, Ord. 27,654) St. Louis County Dept. of Transportation and Public Works · User-friendly edition dated Apr 1, 2020Checked Nov 28, 2026 · Read through a web-fetch/search tool (the site blocks direct downloads); verbatim excerpt saved in raw/Same sections appear on Municode (codified through Ord. 29,532, Feb 17, 2026): library.municode.com/mo/st._louis_county. Confirm the current adopted edition before launch.
  2. St. Louis County Ordinance Guidebook — Building Codes & Permits (Unincorporated, Contractual) St. Louis County PlanningChecked Nov 28, 2026 · Read through a web-fetch/search tool (the site blocks direct downloads); verbatim excerpt saved in raw/Plain-language chart; where it differs from the code (fence height) both are shown.
  3. St. Louis County Ordinance No. 29,445 (2025), amending Chapter 1100 “Code Enforcement Fee Schedule” St. Louis County Council · Adopted Nov 4, 2025; approved Nov 5, 2025Checked Nov 28, 2026 · Full text retrieved; saved in raw/slc/Processing fees may be revised each July 31 (§1100.035).
  4. Residential Building (contact page) St. Louis County Dept. of Transportation and Public WorksChecked Nov 28, 2026 · Read through a web-fetch/search tool (the site blocks direct downloads); verbatim excerpt saved in raw/
  5. St. Louis County Services Portal (Accela) St. Louis CountyChecked Nov 28, 2026 · Read through a web-fetch/search tool (the site blocks direct downloads); verbatim excerpt saved in raw/