Sheet 07 / St. Louis CountyElectrical panel permit
Permit required
Electrical panel permit
in St. Louis County, MO
Permit requiredYes. Electrical service and panel work needs an electrical permit: a $94 minimum plus unit pricing ($12 for a service up to 200 amps).
- Jurisdiction
- St. Louis County, Missouri
- Project
- Electrical panel (electrical panel or service work)
- Issued by
- St. Louis County Dept. of Transportation & Public Works
- Fee data
- Fees verified
- Checked
- Nov 28, 2026
- Sheet no.
- GP-MO-SLC-07
01
Do you need a permit?
- Permit required to install, alter or replace any electrical system regulated by the code, except work exempted by NFPA 70.[1]
02
What it costs
| Item | Amount | Notes & source |
|---|---|---|
| Minimum electrical permit (no plan review) | $94 + unit pricing, rounded up to the next whole dollar | Includes $47 processing and one inspection.[2] |
| Minimum with plan review | $124 + unit pricing | [2] |
| Two inspections | $141 (no plan review) or $171 (plan review), + unit pricing | [2] |
| Service equipment, up to 200 amps | $12 per service | Over 200–400 A: $18; over 400–600 A: $41; over 600 A: $53. Panel boards are priced the same as service equipment (Note C).[2] |
| Electrical outlets | $8 first, $0.75 each additional | [2] |
| Extra inspection | $47 each | [2] |
Fee schedule: Ordinance 29,445, adopted Nov 4, 2025. Processing fees may be revised each July 31.
03
Where and how to apply
Residential Building, St. Louis County Dept. of Transportation and Public Works
41 South Central Ave., 6th Floor, Clayton, MO 63105
Phone 314-615-5184 · Mon–Fri 7:30 a.m.–4:00 p.m.[3]
St. Louis County Services Portal (Accela)[4]
- Start a new application in the County portal, or call Residential Building.
- Estimated construction cost drives the building fee; the Code Official may estimate it by square-foot cost or accept a signed contract or owner affidavit (§1100.040).
04
What we could not verify
What we could not verify or what to confirm
- Whether a given panel swap is billed as one “service”, one “panel board”, or both is the office’s call; the schedule does not say.
- Licensed-electrician rules were not reviewed.
Same project, other places
- Electrical panel permit in City of St. Louis — Likely required
- Electrical panel permit in Fenton — Permit required
- Compare all places for electrical panel
05
Sources
Every figure above comes from the government pages below. Verbatim excerpts and raw downloads are archived with the site data. Not legal advice; see the disclaimer.
- SLCRO Chapter 1115 Building Code §105.1, §105.1.2, §105.2 (2015 ICC codes, user-friendly edition, Ord. 27,654) St. Louis County Dept. of Transportation and Public Works · User-friendly edition dated Apr 1, 2020Checked Nov 28, 2026 · Read through a web-fetch/search tool (the site blocks direct downloads); verbatim excerpt saved in raw/Same sections appear on Municode (codified through Ord. 29,532, Feb 17, 2026): library.municode.com/mo/st._louis_county. Confirm the current adopted edition before launch.
- St. Louis County Ordinance No. 29,445 (2025), amending Chapter 1100 “Code Enforcement Fee Schedule” St. Louis County Council · Adopted Nov 4, 2025; approved Nov 5, 2025Checked Nov 28, 2026 · Full text retrieved; saved in raw/slc/Processing fees may be revised each July 31 (§1100.035).
- Residential Building (contact page) St. Louis County Dept. of Transportation and Public WorksChecked Nov 28, 2026 · Read through a web-fetch/search tool (the site blocks direct downloads); verbatim excerpt saved in raw/
- St. Louis County Services Portal (Accela) St. Louis CountyChecked Nov 28, 2026 · Read through a web-fetch/search tool (the site blocks direct downloads); verbatim excerpt saved in raw/